INTEGRIS Health is Oklahoma's largest nonprofit community health system. In 2021, INTEGRIS announced plans to proceed with a new heart hospital and major ICU expansion and renovation of its existing INTEGRIS Baptist Medical Center in Oklahoma City. The new tower would be constructed on top of an existing parking structure and connect to both new and existing structures.
As INTEGRIS embarked on the project, it became clear that its internal project management team did not have the capacity to execute this complex undertaking.
Hammes was initially engaged in a staff augmentation capacity to provide leadership for the existing project management team. Ultimately, this transitioned to full project management support with multiple Hammes project management professionals engaged.
Enabling work for the project began in October 2021, with the construction of the new heart hospital tower commencing in March 2022. The new six-story tower and 10-story connector to the existing hospital include 64 ICU beds, five ORs (four CVORs and one hybrid OR), and seven minor procedure rooms, including five cath labs and two EP labs. The new tower was completed in March 2024, and the hospital renovation in 2025.




Here are answers to common questions about us.
Let's discuss your project and how we can help drive success for your healthcare system.
Hammes Healthcare provided project management and transition planning services for the INTEGRIS Health Heart Hospital and ICU expansion. Hammes was initially engaged in a staff augmentation capacity and transitioned to full project management with multiple Hammes professionals supporting the program.
The INTEGRIS Heart Hospital and ICU Tower are located at INTEGRIS Baptist Medical Center in Oklahoma City, Oklahoma. INTEGRIS Health is Oklahoma’s largest nonprofit community health system.
The program totals approximately 209,000 square feet, including a six-story heart hospital tower and a 10-story connector to the existing INTEGRIS Baptist Medical Center. The facility includes 64 ICU beds, five operating rooms (four CVORs and one hybrid OR), and seven minor procedure rooms (five cath labs and two EP labs).
Enabling work for the program began in October 2021, with construction of the new heart hospital tower commencing in March 2022. The new tower was completed in March 2024, and the renovation of the existing hospital was completed in 2025.
In-house design and construction teams are sophisticated operating units inside a health system. However, at times even in-house bandwidth and expertise can be exceeded. Acting as an extension of our clients’ teams, our seasoned healthcare project executives work collaboratively alongside healthcare organization’s internal project managers to bring the needed expertise to assigned projects. For INTEGRIS Health, the engagement began as staff augmentation to extend the internal project management team and ultimately transitioned to full project management support with multiple Hammes professionals engaged across the program.